Project Update November 2009
Overview
We are writing to firstly, wish you Eid Mubarak as we prepare in Dubai for the three
day religious festival and the National Day a few days later and then move into
the final month of the Year. Secondly, we wish to update you on progress and to
inform you when we will be able to confirm completion and provide you with an
occupation date. For those that have not made appointments to personally visit the
site, you will be pleased to hear that work continues to progress well. We still await
to receive the formal Building Completion Certificate and permanent power but are
now confidently programming in terms of weeks and days as opposed to months
and weeks. We hope to provide you with some good news when we return after Eid
and will write to inform you as soon as we receive the Authorities official Building
Completion Certificate. We will then be able to confirm how long it will take for the
contractors to hand over the buildings to Asteco Development Management and the
phased timeline for Asteco to handover of the buildings and units to the individual
customers.
From the photographs, you will see that work on the beach has started and
progressed since we last wrote. The landscaping on the podium is maturing and the
two restaurants and bar facilities are externally complete. The swimming pool has
been full for sometime and the lazy river is due to be filled shortly. Internally, two
additional show apartments have been completed and furniture packages installed to
complement the third show unit. The offices for the handover and co-ordination and
Sales staff have been prepared and made ready in anticipation. Work continues on
the detail within the apartments and externally in the corridors and entrance lobbies.
Behind the scenes, the basement car parks are nearing completion and additional
design and access controls are being refined and added to ensure residents privacy is
respected uninvited visitors will not able to gain access to the podium’s facilities. The
co-ordination team is preparing and assembling all documentation in parallel to the
Strata team and the external lawyers to ensure that the legal structure is correct and
complies with both the new Jointly Owned Property Law and also practical reality -
to ensure the long term success of the Oceana Development. The FM contractor is
due to be publicly appointed very shortly and is preparing to mobilize immediately
to begin refining and checking the plant and machinery in advance of the handover.
In conclusion, please be assured that Seven Tides and Asteco Development
Management and Property Management are collectively working very hard in your
interest to deliver the product that you purchased. The journey is almost at an end
but we are aware that there is still time for surprises but we emphasize that Seven
Tides is doing its professional up most to forsee and avoid and or if necessary address
issues at its expense if they arise. We are now on the final straight and will write very
shortly after Eid to provide dates for the handover.
Below, the Podium’s landscaping design is superimposed over a photo of the actual work on
site to date, to provide you with an insight into the final product.
Thanking you.
Yours Sincerely,
Ian Hollingdale
Head of Project The Palm